| Globe - Lordsburg Highway (US 70) (PIMA-SAFFORD) Slope Flattening |
| |
Project No.: |
070 GH 330 H674901C / 070-A-(203)A |
| |
Location: |
Graham County on US 70 between the towns of Pima and Safford (MP 330.94 to MP 338.36) |
| |
Contractor: |
MCCAULEY CONSTRUCTION INC. |
| |
Description: |
The work consists of extending and flattening sections of the highway embankment slopes on the north side of US 70; extending concrete box culverts and pipe culverts; constructing roadside drainage swales; and spot drainage improvements at eight locations with hand-placed and grouted riprap, concrete header, gabion bank protection, drainage channel, sidewalk reconstruction, driveway replacement, and other related work. |
| |
|
Duration: |
Time allowed for the completion of this project is 180 working days. |
| |
|
|
|
| Safford 8th Avenue Bridge |
| |
|
Project No.: |
000 GH GGH SB41601C / BR-GGH-0(007)A |
| |
|
Location: |
North of the City of Safford in Graham County at the 8th Avenue Bridge over the Gila River |
| |
|
Contractor: |
AMES Construction, Inc. |
| |
|
Description: |
The project work will include the construction of a new bridge crossing over the Gila River and re-align both roadway approaches. The new structure will be located adjacent to an upstream of the existing structure. Additional work includes placement of pavement markings, signs, seeding, and other related work. The Construction Supervisor of this project is Paul David, Senior Resident Engineer, located in the Safford Construction Office, phone 928.432.4936. Work on the project began in April 2009. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project is 215 working days. |
| |
|
|
|
| SR 78 Mule Creek Highway Jake’s Corner Realignment |
| |
Project No.: |
078 GE 169 H666901C |
| |
|
STP-078-A(201)A |
| |
Location: |
State Route 78 between milepost 169.92 and 170.17 in Greenlee County |
| |
Contractor: |
CKC Construction & Materials, LLC. |
| |
Awarded: |
June 18, 2010 |
| |
Description: |
Work includes widening and realigning SR 78 to flatten the horizontal curve and to raise the roadway profile. The work also includes a new cross drainage pipe culvert, signing, pavement marking and other related work. |
| |
|
Duration: |
Time allowed for the completion of the work included in this project is 95 working days. |
| |
|
Construction Alert: |
August 10, 2010 |
| |
|
|
Realignment under way on State Route 78 |
| |
US 191 Bowie Junction – Safford Highway Segment V |
| |
|
Project No.: |
191 GH 100 H818501C |
| |
|
|
STP-191-B(201)A |
| |
|
Location: |
Graham County on US 191 at milepost 100.59 to milepost 104.52, approximately 15 miles south of Safford |
| |
|
Contractor: |
|
| |
|
Awarded: |
Design-Build Proposals due by July 26, 2010 |
| |
|
Description: |
The work includes the construction of two new northbound lanes east of the existing roadway with asphaltic concrete and asphaltic rubber friction course; construction of turnouts and reconfiguring the “T” intersection with SR 266; extend five reinforced concrete box culverts; extend 13 existing pipe culverts; construct 14 new pipe culverts; construct 23 new lateral storm drains and catch basins; overlay the existing pavement with asphaltic concrete and asphaltic rubber friction course; erosion control; seeding; signing; pavement marking; and other related work. |
| |
|
Duration: |
The Department-Determined Construction Phase Time for substantial completion of the work shall be 500 calendar days. |
| |
|
|
|
| |
|
|
|
US 191 Dial Wash to Ten Ranch Segment II |
| |
|
Project No.: |
191 CH 087 H503704C |
| |
|
|
ARRA-191-N(200)A |
| |
|
Location: |
The project extends from MP 87.90 to MP 94.70 thru Cochise and Graham Counties on US 191 approximately 20 miles south of Safford |
| |
|
Contractor: |
C.S. & W. Contractors, Inc. |
| |
|
Awarded: |
June 18, 2010 |
| |
|
Description: |
The work includes construction of two lanes NB east of the existing roadway and a mill and overlay of the existing pavement, construction of turnouts, eleven inlet and outlet extensions at six existing box culverts, extension of ten drainage pipes and installation of seventeen new pipes and other drainage improvements, erosion control, seeding, signing and striping and other related work. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project will be 290 calendar days. |
| |
|
Construction Alert: |
August 10, 2010 |
| |
|
|
|
US 191 Guthrie Bridge No. 352 Removal |
| |
|
Project No.: |
191 GE 153 H641701C |
| |
|
|
191-C-NFA |
| |
|
Location: |
Greenlee County on US 191 from milepost 152.95 to milepost 154.13, at the Gila River |
| |
|
Contractor: |
|
| |
|
Awarded: |
Bid Opening July 22, 2010 |
| |
|
Description: |
The proposed work includes removing the existing Guthrie Bridge. The superstructure will be removed in its entirety, and the substructure removal will be per the limits specified in the Project Plans and Special Provisions. Also included in the proposed work is removal of construction access roads, obliteration of the abandoned portion of US 191, final grading and vegetation establishment and other related work. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project will be 180 calendar days. |
| |
|
|
|
US 191 JCT US 70 Back Country Byway |
| |
|
Project No.: |
191 GH 131 H792201C |
| |
|
|
STP 191-C(207)A |
| |
|
Location: |
US 191 in Graham County approximately 10 miles east of Safford beginning at milepost 131.0 and extending to milepost 137.0 |
| |
|
Contractor: |
|
| |
|
Awarded: |
Bid Opening August 6, 2010 |
| |
|
Description: |
The proposed work consists of milling and replacing asphaltic concrete. Additional work includes replacing existing pavement markings, pavement markers, and other related items. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project will be 25 working days. |
| |
|
|
|
US 191 Ward Canyon Bridge Repair |
| |
|
Project No.: |
191 GE 162 H671301C |
| |
|
|
STP-191-C(208)A |
| |
|
Location: |
US 191 milepost 162.65 in Greenlee County |
| |
|
Contractor: |
C S Construction, Inc. |
| |
|
Awarded: |
July 16, 2010 |
| |
|
Description: |
The work includes construction of a new retaining wall, drainage channel floors, concrete key and slope paving to protect the slope at one of the abutments of the Ward Canyon Bridge and other associated work. |
| and |
|
US 191 San Francisco Bridge Replacement |
| |
|
Project No.: |
191 GE 163 H670801C |
| |
|
|
BR-191-C(205)A |
| |
|
Location: |
US 191 milepost 163 in Greenlee County |
| |
|
Description: |
The project consists of removing the existing 366 foot long steel girder bridge, and replacing it with a 317 foot long, eight span closed frame continuous slab bridge. The work also includes removal and construction of concrete curb and gutter, sidewalk and driveways, construction of two approach slabs, riprap, placement of AC on the approach slabs and other related work. |
| |
|
Duration: |
The time allowed for the completion of the work included in these two projects (Ward Canyon Bridge Repair and San Francisco Bridge Replacement) will be 200 working days. |
| |
|
|
|
| |
|
|
|
| |
Charleston Road Widening - Sierra Vista |
| |
|
Project No.: |
0000 CH SVS SS74501C |
| |
|
|
ARRA-SVS-0(204)A |
| |
|
Location: |
In Cochise County within the City of Sierra Vista on Charleston Road, beginning west of Colombo Avenue and extending east of Fighting Colt Drive. |
| |
|
Contractor: |
K E & G Construction, Inc. |
| |
|
Awarded: |
April 16, 2010 |
| |
|
Description: |
The proposed work consists of reconstructing and widening Charleston Road. The work includes roadway excavation; grading; furnishing and placing aggregate base, asphaltic concrete pavement and asphalt rubber friction course; replacing pipes; constructing new 3 barrel precast RCB Culvert; pavement marking; curb and gutter; signing; signals; and other related work. |
| |
|
Duration: |
The time allowed for the completion of the work is 100 working days. |
| |
|
|
|
I-10 & SR 90 Traffic Interchange (TI) |
| |
|
Project No.: |
010 CH 300H650401C |
| |
|
|
NH-STP-HSIP-TEA-010-E(200)N |
| |
|
Location: |
Cochise County on I-10 at the State Route 90 Traffic Interchange near the City of Benson |
| |
|
Contractor: |
|
| |
|
Awarded: |
|
| |
|
Description: |
The project will reconstruct the I-10/SR 90 TI overpass structures, SR 90 below the overpass, entrance and exit ramps in both directions, realign and reconstruct I-10 mainline west of the TI, construct three access roads (W. Dark Star Road, N. Vidal Trail and W. Calvary Lane), drainage improvements, lighting, utility relocations, signing and marking, and other related work. |
| |
|
Duration: |
The time allowed for the completion of the project is 500 working days. |
| |
|
|
|
SR 80 Tombstone - Jct SR 90 |
| |
|
Project No.: |
080 CH 318 H574101C |
| |
|
|
STP-080-A(206)A |
| |
|
Location: |
Cochise County on State Route 80 between the Town of Tombstone and the junction with State Route 90 |
| |
|
Contractor: |
Bid Opening September 16, 2010 |
| |
|
Awarded: |
|
| |
|
Description: |
The work consists of extending box culverts and pipe culverts, removing and replacing pipe culverts and signing, removing embankment curb and spill ways, and performing other related work. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project will be 235 working days. |
| |
|
|
|
SR 80 East Douglas – Rodeo Highway |
| |
|
Project No.: |
080 CH 368 H658001C |
| |
|
|
STP-080-B(200)A |
| |
|
Location: |
SR 80 near the City of Douglas in Cochise County |
| |
|
Contractor: |
Fisher Sand & Gravel Co. DBA Southwest Asphalt Paving |
| |
|
Awarded: |
June 28, 2010 |
| |
|
Description: |
The project starts at MP 368.40 and extends northeast to MP 378.51. The work includes milling and replacing asphaltic concrete pavement, placing an AR-ACFC overlay, reconstructing guardrail and other related items. |
| |
|
Duration: |
Time allowed for the completion of the work included in this project will be 125 working days. |
| |
|
Construction Alert: |
August 10, 2010 |
| |
|
|
Chip seal work under way on State Route 80 in Bisbee |
| |
|
|
|
| SR 82 San Pedro River Bridge |
| |
|
Project No.: |
082 CH 061 H749701C |
| |
|
|
STP-082-A(200)A |
| |
|
Location: |
Cochise County on State Route 82 at the San Pedro River Bridge at Milepost 61.2 approximately 8 miles west of the City of Tombstone |
| |
|
Contractor: |
Bison Contracting Co., Inc. |
| |
|
Awarded: |
December 18, 2009 |
| |
|
Description: |
The proposed scour retrofit work consists of constructing reinforced concrete slab at the piers and abutments, repairing the west abutment and performing other related work. |
| |
|
Duration: |
The time allowed for the completion of the work is 95 working days. |
| |
|
|
|
| SR 90 Babocamari River Bridge |
| |
|
Project No.: |
090 CH 311 H804201C |
| |
|
|
NH-090-A(202)A |
| |
|
Location: |
Cochise County on State Route 90 between Milepost 311.77 and Milepost 311.83 within the Town of Huachuca City |
| |
|
Contractor: |
|
| |
|
Awarded: |
|
| |
|
Description: |
The work consists of milling existing asphaltic concrete pavement and replacing it with new asphaltic concrete and asphaltic friction course. Additional work includes the replacement of the existing pavement markings. |
| |
|
Duration: |
The time allowed for the completion of the project is 10 working days. |
| |
|
|
|
| SR 92 Carr Canyon to Hunter Canyon |
| |
|
Project No.: |
STP-092-A(001)B / H459601C |
| |
|
Location: |
Project Map |
| |
|
Description: |
Project Web site |
| |
 |
Traffic Alert: |
June 14 - 18, 2010 |
| |
|
|
Lighting Update on Hereford Road |
| |
|
|
|
US 191 Glenn Road to Elfrida |
| |
|
Project No.: |
191 CH 005 H791601C |
| |
|
|
STP-191-A(201)A |
| |
|
Location: |
The project begins at MP 5.00 on US 191 and extends north to MP 20.50 in Cochise County approximately 5 miles north of Pirtleville |
| |
|
Contractor: |
Cactus Transport, Inc. |
| |
|
Awarded: |
June 18, 2010 |
| |
|
Description: |
The work consists of placement of a double application seal coat, pavement markings and other miscellaneous work. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project will be 50 working days. |
| |
|
Construction Alert: |
August 10, 2010 |
| |
|
|
Chip seal work begins this week on US 191 |
| |
|
|
|
| |